Thursday 16 September 2010

Work starts on Monday at Napket
in Vigo St, Piccadilly. Extensive alterations are
being carried out to the kitchen and front
of house areas. The existing basement is to be
upgraded with additional work space
and equipment to create a fully functional
kitchen. The front of house is to receive a major refit
to improve the flow of customers through
the retail areas.

Bluecrow are handling all aspects of the
project from the initial client brief through to
handover.

Friday 10 September 2010

Point of no return at Sardo Cucina in London as temporary steel columns are installed to support the residential flats above. While Bluecrow were carrying out extensive refurbishment work to the building it was discovered that the existing timber structure had deteriorated to such an extent that it was no longer strong enough to support the proposed new Italian delicatessen and the accommodation above.


Structural steel engineers have now designed additional steelwork to rectify the problem which Bluecrow are currently installing in the basement.


Due to the care and attention by all concerned minimum disturbance has been caused to the surrounding neighbours with only a slight extension to the original project programme.

www.bluecrowprojects.com/wood_from_trees.html

Tuesday 13 July 2010

We have just completed the retail fit out and alterations to the Customer Living Room at the Bentley Motors manufacturing plant at Crewe. For more pictures please go to http://www.bluecrowprojects.co.uk/retail_fit_out_bentley_motors

Thursday 13 May 2010

Bentley Motors Ltd

Confirmation received today that we have been chosen to carry out the complete re-fit of the customer living room at Bentley Motors Ltd, Crewe.

Monday 22 February 2010

Exciting New Design & Build Project

Exciting new design and build project to transform a derelict country pub into a traditional inn with up market 90 seat restaurant and bar area. The property is situated on a busy A road in the beautiful Cotswold countryside. Two local businessmen have purchased the site and approached Bluecrow to manage the project from conception through to handover.

Working with designLSM and the clients we now have an approved concept design, which includes back of house kitchen and first floor accommodation. We are currently working on final project costs with a view to starting construction on site in April.

http://www.bluecrowprojects.com/

Monday 18 January 2010

We would like to say a big thank you to all our clients and consultants who we have worked with over the last year. We have carried out a variety of shopfitting and refurbishment projects throughout a busy 2009. There has been a promising start to 2010 and we look forward to hopefully working again with you soon. For more information on us and our featured projects, like the refurbishment of Jamie Oliver's Fifteen Restaurant in London above, please visit our site at http://www.bluecrowprojects.com/.